Highland Park's $22.2 million rebuild where Wycliffe and Fitzhugh avenues meet Turtle Creek was scheduled to begin in October 2026, and the plan sets one fixed point. The Town of Highland Park lists "preservation of the existing water level in Connor Lake" among the project's stated benefits. The roadway around the lake gets raised, narrowed and rebuilt from the utility lines up. The water itself is meant to look the same when the work is done.
The construction runs long, with completion targeted for June 2028, because so much is being swapped out around something that has to stay put.
The Road Is Actually a Dam
The pavement on Wycliffe between St. Johns Drive and Lakeside Drive does more than carry traffic. It is the dam that holds back Connor Lake, and under the plan it will be removed and rebuilt as a bridge, as People Newspapers reported in June. The Texas Commission on Environmental Quality currently classifies the structure as high hazard. The Town's stated goal, laid out on its project FAQ, is to have it reclassified as low hazard.
Engineers presented the physical design at a December 2024 special Town Council meeting. According to People Newspapers' account of that meeting, it calls for raising the roadway 2.5 feet, building a weir and a bridge, removing the standpipe, and widening the downstream channel. The same goals list included keeping Connor Lake at its existing level.
| Wycliffe today | Wycliffe after the project | |
|---|---|---|
| Structure at Turtle Creek | Roadway dam | Weir and bridge |
| Travel lanes | Three | Two, plus a dedicated left-turn lane across the bridge |
| Roadway height | Current grade | Raised about 2.5 feet |
| Standpipe | In place | Removed |
| Connor Lake | Current water level | Same water level |
The weir is how the last row works. A weir is a low, engineered wall that holds water at a set height and lets it spill over in a controlled way. It replaces the dam's job of holding the lake while the road rises above it on a bridge.
Two Lanes Where There Were Three
The detail most likely to change a daily drive once construction ends is the lane count. The Town says Wycliffe will go from three lanes to two, with a dedicated left-turn lane across the bridge "similar to existing conditions."
Losing a lane on a cut-through between the Park Cities, Oak Lawn and Uptown sounds like a recipe for backups. The Town answered that worry by commissioning traffic modeling, which it says "shows no significant change in traffic flow under the proposed configuration." Anyone who wants to check can watch the side-by-side simulations: one shows existing traffic conditions and the other the proposed lane reduction.
The narrower road also connects to the promise about the lake. A two-lane bridge, upgraded pedestrian paths and new landscaping are all part of the finished corridor. The Town says many of the design elements were "thoughtfully influenced by residents."
A Design Residents Pushed On
That resident influence did not come easily. At the December 17, 2024 special meeting, People Newspapers reported that all twelve rows were filled six seats deep and extra chairs still could not hold the crowd. Residents raised concerns about how the structure would look, about traffic disruption, and about whether they had enough say.
The Town's response was the Wycliffe Working Group, made up of Highland Park and Dallas residents who met with Town staff and the technical consultants. In its notice for a June 18, 2025 Town Hall, the Town said the group focused on public safety, traffic management, aesthetics and long-term community benefit, and that its recommendations had been "fully adopted by the Town Council."
By August 2025, Engineering Director Lori Chapin was describing the work as a technical and legal necessity, according to People Newspapers. That report said some residents at the June Town Hall asked about timelines, street closures and access to their homes, while several praised the project.
Twenty Months of Rotating Closures
On September 15, 2026, the Town Council approved a $22,205,303 construction contract with low bidder Rebcon. People Newspapers reported that construction was slated to begin in October and finish by June 2028, weather permitting, with Wycliffe Avenue closed between Abbott Avenue and Oak Lawn Avenue while the project is underway. The start date has moved before. In August 2025 the target was January 2026, and the Town's FAQ later listed June 2026.
Wycliffe is not the only street affected. The Town expects closures or restricted access at different phases on:
- Wycliffe Avenue
- Fitzhugh Avenue
- St. Johns Drive
- Lakeside Drive
- Turtle Creek Boulevard
The Town says these streets will not all be affected at the same time, and that it will put up detours, signage and traffic control as each phase begins.
Fitzhugh has already shown what a phase looks like. In late June 2026, utility work narrowed Fitzhugh to one lane during working hours from just west of the Katy Trail to Oak Lawn Avenue, then reopened it to two lanes after hours. Highland Park Department of Public Safety Lt. Lance Koppa told People Newspapers that AT&T expected to finish in mid-July, with Oncor starting after that.
For households right next to the work, the Town has made specific commitments. The Town says it will keep access open for mail, package deliveries, visitors and utility crews, and fire, police and EMS are to have immediate access at all times. Parking near the construction site will be limited to residents. Crew parking is to be placed where it disturbs nearby blocks as little as possible.
What Gets Replaced Underneath
Part of the reason the corridor stays torn up so long is buried. The project relocates and replaces the Town's 30-inch Turtle Creek interceptor, plus 8-inch water lines and 8-inch and 18-inch wastewater collectors. The City of Dallas is enlarging a 10-inch wastewater line to 18 inches and replacing a 16-inch water line. Oncor, Atmos, AT&T and Spectrum are coordinating their own relocations, and the Town says any brief service interruptions will be announced in advance.
Because the buried lines serve more than one city, the bill is shared too. The Town says about 72 percent of the estimated $22 million cost comes from outside sources:
| Contributor | Role in funding |
|---|---|
| TxDOT | 80/20 federal funding match |
| Dallas County | 50/50 cost-sharing agreement |
| TCEQ | Grant supporting design costs |
| City of Dallas and City of University Park | Financial participation |
| Town of Highland Park | About $6.2 million from local tax dollars |
The same September council meeting also approved construction contracts for the Eastern Avenue Reconstruction Project, the Douglas Avenue Reconstruction Project and the 2026 Drainage Easement Improvements Project.
Where Closure Notices Will Appear
The Town plans to announce each phase change ahead of time through several channels:
- The Town's Wycliffe Avenue Reconstruction Project page on hptx.org, set up as the central place for construction alerts and milestones
- Blue Zone notifications
- Town newsletters and social media
- An Owner's Representative assigned only to this project, who serves as the on-the-ground contact for affected residents
Signing up for Blue Zone alerts is the most direct way to hear about a closure on St. Johns or Lakeside before it shows up on your way out the door.
If you live near Turtle Creek and are planning a sale, a purchase or a remodel that could overlap with the work through 2028, we're glad to talk through how the construction schedule and access plans might affect your timing. Holly Davis & Amy Farris keep a close eye on Highland Park's corridor projects so our clients can plan around them. Contact Us.